|
The primary bridge will begin on the west side of Black Narrows at Route 175
and span north to connect with Maddox Boulevard in town at the Main Street
intersection. A bascule bridge will be installed as part of the new span that
crosses over Lewis Creek Channel.
This new primary bridge will allow motorists to access Marsh Island via a
second bridge called the Marsh Island Connector. The Marsh Island Connector will
exit onto Marsh Island at the same location as the soon to be demolished Black
Narrows Bridge. The Chincoteague Channel Bridge also will be demolished
following construction.
At this time, American Bridge has completed the concrete bridge test pile
phase, and crews are now driving production piles. Furthermore, the contractor
is driving 48-in. (122 cm) piles at the bascule pier and placing pier caps on
some of the piles. American Bridge brought in its Manitowoc M250 barge-mounted
crane to drive 36-in. (91 cm) piles below the mud line, among other tasks.
American Bridge has Kevin Moynihan, project manager, and Tom Dey, assistant
project manager, working on the job site. According to Dey, the Manitowoc M250
has a Bruce hydraulic pile hammer attachment that is used for work on the 14-in.
(36 cm) steel pipe piles at the abutments.
"It is the second largest hydraulic hammer in the United States," said
Dey.
In addition, American Bridge is using another Manitowoc, a 4100, which is on
a flexifloat. The company is also making use of a Tadano rubber-tire 60-ton (54
t) capacity crane.
Temporary bridges, or trestles, had to be built prior to constructing the new
bridges, so American Bridge brought in two barge-mounted crawler cranes that
remain on-site. An American 9320 crane is still being used, and an American 9299
crane is now located at abutment A.
Additional work that has been finished includes the completion of the
concrete retaining wall along the Black Narrows marsh land. Six massive
transmission line poles have been installed in preparation of the power company
relocating power lines. Concrete pours will begin in March, which includes
pouring the foundation for the moveable span pier and pouring the pier cap
beams.
This project comes with environmental protection restrictions because the
Colonial-nesting bird chooses to mate and nest in the waters surrounding
Chincoteague Island. Tia Freeman, VDOT's public relations specialist, said that
the "environmental protection restrictions were lifted in the Fall and are
coming back April 1 through Sept. 1."
When asked if work has to stop entirely on the project due to the
environmental concerns, Dey said, "No. We just move from one area to another and
away from the marsh."
During the restricted period, no work can be performed at what Freeman calls
"the transition zone between the existing causeway and the new bridge." Still,
there are plenty of other tasks that can be performed until September. Even so,
VDOT and the contractor constantly monitor construction activities to ensure
compliance with environmental regulations.
The numerous benefits resulting from the new bridges will be worth the wait
for the townspeople and the many yearly visitors. Traffic congestion in downtown
Chincoteague will be reduced, boaters will have better channel access and the
number of necessary bridge openings will be reduced. In addition, the wider
lanes and shoulders will enhance motorists' safety and industrial access may
improve because VDOT will be able to consider permits for overweight loads.
CEG
Display On: 3/12/2008 |